News from MMWD Blvd Pipeline and Road Projects on SFD Blvd. April 16, 2025
Three infrastructure improvement projects on Sir Francis Drake Boulevard in Ross are scheduled to begin soon. We are notifying you so that you can help inform your constituents. All three projects will likely result in traffic impacts for their duration. Please allow extra travel time in the coming months and consider using alternate routes.
Sir Francis Drake Blvd Projects � Pipeline: April 26 � June 15. MMWD will be installing 2700 feet of pipe on Sir Francis Drake (SFD) Boulevard between Winship Avenue and Lagunitas Road. Work hours are 8 am-6:30 pm weekdays. Two lanes will be open at all times.
� Sidewalks: July 1 � August 15. The Town of Ross will be installing sidewalks on SFD Blvd between Bolinas Avenue and Kentfield.
� Road resurfacing: August 15 � August 31. The Town of Ross will be repaving SFD Blvd between Bolinas Avenue and Kentfield.
Lagunitas Road Project The Town of Ross has an additional project scheduled this year. The town is replacing the Lagunitas Road Bridge between June 15 and October 31.
Additional Information Detailed information about all the projects, including the work schedules and status updates, will be available online: www.townofross.org (all projects) orwww.marinwater.org (pipeline only). MMWD�s project hotline phone number is 945-1541.
If you have any questions about MMWD�s project, please e-mail Dick Paulson or 945-1569. For questions about the Town of Ross projects e-mail Mel Jarjoura or 453-1453, ext. 119.
Thank you for your patience as we undertake these important infrastructure projects.